Subcontractor Wins Interest and Fees

In a dispute over a Delaware County water plant project that resulted in claims of delay, liquidated damages, disputed change orders and Ohio’s Prompt Pay Act, our subcontractor client was awarded almost all of its claim after the jury threw out the contractor’s counterclaim. The contractor was found to be in bad faith and in violation of Ohio’s Prompt Payment Act, which entitled our client to 18% interest and attorney’s fees.