Home
About Us
Services
People
News
Publications

Well done, Ollie. book

Advocate: The Litigation Newsletter

Business, Tax & Securities Alert

Construction Law Newsletter & Alert

Estate Planning & Probate Newsletter

Housing Newsletter

Labor & Employment Law Publications

Subscribe

Opt-Out

Events
Careers
Offices
Contact
Press
RSS Web Feeds
 

April 7, 2008

Contractors Score Victory With Broad Interpretation of “Delay.”

Gregory photo
Donald W. Gregory,
Construction Law
Chair

The Ohio Supreme Court case of Dugan & Meyers, with its strict insistence on notice, greatly worried contractors who believed that they were being forced to give almost daily written notice of their project impacts and delays or risk the loss of an otherwise viable claim. Meanwhile, owners confidently believed that they finally had a shield against claims for delay costs at the conclusion of a project. Yet we cautioned clients that the Dugan & Meyers case might have little long-term precedential value as it was decided under a contract signed before the Fairness in Construction Contracting Act (R.C. 4113.62) was enacted, which (in relevant part) provides:

Any provision of a construction contract * * * that waives or precludes liability for delay * * * when the cause of the delay is a proximate result of the owner’s act or failure to act, or that waives any other remedy for a construction contract when the cause of the delay is a proximate result of the owner’s act or failure to act, is void and unenforceable as against public policy.

A case decided in the last few days by the Franklin County Court of Appeals has broadly defined “delay” within the meaning of the statute to include acceleration or other impact claims. Cleveland Construction, Inc. v. Ohio Public Employees Retirement System, No. 07AP-574 (April 3, 2008). Perhaps even more importantly, the Court has ruled that the statute eliminated the need for a time extension request as required by the contract. This case means that contractors will need to worry less about giving formal written notices of delay throughout the course of the project, and that owners have lost the means to defend an otherwise valid delay or impact claim on procedural grounds, such as lack of timely notice or the failure to timely request a time extension.

There is no question that this decision (if not reversed by the Ohio Supreme Court) will embolden contractors to assert claims, even long after the original delay occurrence, when the cause of the delay is arguably the owner’s “actions or inactions.” The pendulum has swung from owner to contractor with respect to delay claims in Ohio -- at least for now.


Credits

Kegler, Brown, Hill & Ritter's Construction Law Alert is prepared by the Construction Law practice group.

To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.

The Construction Law Alert is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.

© 1993-2008, Kegler, Brown, Hill & Ritter Co., L.P.A.

Mediation Services

Well done, Ollie.

Kegler Brown Publications

State Capital Group

Kegler, Brown, Hill & Ritter© 2008, Kegler, Brown, Hill & Ritter Co., LPA.  Disclaimer  |  Privacy Statement  |  Site Map

Member firms of the State Capital Group practice independently and not in a relationship for the joint practice of law.