The Ohio Supreme Court case of Dugan & Meyers, with
its strict insistence on notice, greatly worried contractors who
believed that they were being forced to give almost daily written
notice of their project impacts and delays or risk the loss of an
otherwise viable claim. Meanwhile, owners confidently believed that
they finally had a shield against claims for delay costs at the
conclusion of a project. Yet we cautioned clients that the Dugan
& Meyers case might have little long-term precedential
value as it was decided under a contract signed before the Fairness
in Construction Contracting Act (R.C. 4113.62) was enacted, which
(in relevant part) provides:
Any provision of a construction contract * * * that waives
or precludes liability for delay * * * when the cause of the delay
is a proximate result of the owner’s act or failure to act,
or that waives any other remedy for a construction contract when
the cause of the delay is a proximate result of the owner’s
act or failure to act, is void and unenforceable as against public
policy.
A case decided in the last few days by the Franklin County Court
of Appeals has broadly defined “delay” within the meaning
of the statute to include acceleration or other impact claims. Cleveland
Construction, Inc. v. Ohio Public Employees Retirement System,
No. 07AP-574 (April 3, 2008). Perhaps even more importantly, the
Court has ruled that the statute eliminated the need for a time
extension request as required by the contract. This case means that
contractors will need to worry less about giving formal written
notices of delay throughout the course of the project, and that
owners have lost the means to defend an otherwise valid delay or
impact claim on procedural grounds, such as lack of timely notice
or the failure to timely request a time extension.
There is no question that this decision (if not reversed by the
Ohio Supreme Court) will embolden contractors to assert claims,
even long after the original delay occurrence, when the cause of
the delay is arguably the owner’s “actions or inactions.”
The pendulum has swung from owner to contractor with respect to
delay claims in Ohio -- at least for now.
Credits
Kegler, Brown, Hill & Ritter's Construction Law Alert is prepared by the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Alert is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.