The construction industry traditionally has been receptive to arbitration
as a speedy and cost-effective alternative to litigation. However,
recent criticisms of arbitration have led major trade association
forms like AIA and ConsensusDOCS to give parties a chance to choose
either arbitration or litigation by checking a box in the contract
form.
Courts also have been hard on arbitration recently, particularly
when involving consumers or residential construction. Several recent
cases have refused to enforce arbitration provisions, finding them
unconscionable in certain circumstances. A contract clause is unconscionable
where there is an absence of meaningful choice for the parties,
together with draconian contract terms unreasonably favorable for
the other party.
A recent Ohio court took this trend further yet when it ruled that,
by failing to include in the arbitration provision a notice that
the homeowner was waiving its constitutional right to a jury trial,
the arbitration clause was unenforceable. Bayes v. Merle’s
Metro Builders, 2007-Ohio-7125. If this trend continues, arbitration
will no longer be a speedy and cost-effective alternative for consumer
disputes and overwhelmed courts will have no one to blame but themselves.
In the interim, entities doing business with consumers should exercise
great care to draft arbitration clauses that go to great lengths
to explain the significance of the arbitration clause (i.e. waiving
a jury trial) and to provide a “level playing field”
in the arbitration process, in order to increase the chances the
clause will be found enforceable if challenged.
Even supporters of design-build recognize that since design-build
participants cannot be identified until bids are received, this
often is too late to meaningfully participate in an efficient, integrated
design.
Construction players tired of fragmented adversarial and linear
relationships who desire a more team-based, collegial approach are
now implementing Integrated Project Delivery - IPD.
Technology advances like Building Information Modeling - BIM –
in which computer 3-D modeling allows the team to refine the design
up-front to minimize delays, conflicts and change orders during
construction, have also encouraged the use of an IPD approach. Under
IPD, all members of the trusted construction team, owner, designer,
contractor and even subcontractors, come together early on to design,
budget and ultimately build the Project, frequently with risk and
cost savings being equitably shared on an upfront basis. Under IPD,
all parties are incentivized to work together for the common good
of the Project.
While the IPD process is relatively new and requires a trusted team,
many working under this project delivery system report much greater
satisfaction, cooperation and savings in time and cost over traditional
project delivery systems.
For now, IPD is primarily utilized by sophisticated and involved
owners on private work. There is no way to legally utilize this
method on Ohio public work at the present time.
While IPD and BIM are well under way on complex jobs, contract
documents are trying to catch up. The ConsensusDOCS group, consisting
of more than two (2) dozen national trade associations representing
owners, sureties, contractors and subcontractors, have come together
to endorse dozens of contract documents.
Perhaps the most unique is the ConsensusDOCS 300 form designed for
a Tri-Party Agreement (designer, owner and contractor) on a collaborative
IPD project. In this contract, the parties share project risks and
costs savings measured against a Project Target Cost Estimate. The
Contractor (and Subcontractors) are to work together with the Architect
and Owner to continually bring value through improved quality, cost
savings or constructability. All have a common interest in the overall
success of the Project.
It is common for subcontractors to be told that they “have
the job” and to start work before they receive a signed subcontract
from the contractor. A recent case out of New York demonstrates
the risk of doing so. Jordan Panel Systems v. Turner Construction,
841 N.Y.S. 2d 561 (App. Div. 2007).
In this case, the contractor sent the subcontractor a “term
sheet,” which said that while the subcontractor could not
withdraw his bid, the contractor reserved the right not to execute
the subcontract “pending an internal review and prior approval
by the owner where appropriate.”
Later the contractor told the subcontractor he had been awarded
the subcontract and to proceed with design development. However,
the contractor subsequently told the subcontractor that his involvement
was terminated and the work given to a competitor. When the unhappy
subcontractor sued, the Court ruled for the contractor saying that
the subcontractor voluntarily assumed the risk by beginning work
without a signed subcontract.
While this case revolved around a contractor’s not standing
behind his oral promises and hiding behind his written disclaimers,
subcontractors have been similarly successful when they put disclaimers
in their bids. For example, in applying New Jersey law, a subcontractor
prevailed when he walked away from his bid because the bid provided
that it was for informational purposes only and not a firm offer.
Fletcher-Harlee Corp. v. Pote Concrete Contractors, 482
F.3d 247 (3d Cir. 2007).
These cases demonstrate the risk of the legal fine print and the
perils that occur when project team members do not keep their commitments
to each other.
• Don Gregory has been selected by his peers for inclusion
in the 25th anniversary edition of The Best Lawyers in America®
in the specialty of Construction Law. Selection to Best Lawyers
is based on an exhaustive and rigorous peer-review survey comprising
more than 2 million confidential evaluations by the top attorneys
in the country.
• Don Gregory will be speaking at the Ohio Construction Conference
on February 26, 2008, on the new ConsensusDOCS. The Conference will
feature renowned speakers and presenters representing the construction
industry.
• Mike Madigan will be speaking on Ohio's Fairness in Construction
Contracting Act at the Annual Meeting of Flexible Pavements on March
19, 2008.
• The Construction Law group will be hosting a seminar on
April 30, 2008, that will focus on “Current Subcontract Issues.”
For more information or to register to attend the seminar, please
visit www.keglerbrown.com/events.
Credits
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.