There are ten key "commandments" in Ohio that govern
construction law. Remember these and you will hopefully avoid
any biblical disasters.
Thou shall pay promptly.
ORC §4113.61: Ohio requires contractors to pay their subs
within 10 calendar days after receipt of the payment from the
owner for that work or face 18% interest per annum and attorney's
fees.
Thou shall not hide behind "no damage for
delay."
ORC §4113.62(C)(1) and (2): Ohio finds "no damage for delay" clauses
unenforceable when the cause of the delay is the owner's "actions
or inactions."
Thou shall not hide behind final payment.
ORC §4113.62(B): Ohio does not recognize final payment
as a defense when there is prior written notice of a claim
before
final payment is received.
Thou shall be responsible for
one's own
negligence, in whole or in part.
ORC §2305.31: Ohio's anti-indemnity statute makes unenforceable
any indemnity provision in a construction contract that attempts to make one
responsible for another's negligence for personal injury or property
damage.
Thou shall be permitted to "pay if paid" (but
liens still may be filed).
ORC §4113.62(E): Unambiguous "pay if paid" clauses
are enforceable, but do not bar the timely filing of mechanic's
liens.
Thou shall go forth to arbitration.
ORC §2711.01: Ohio's public policy favors arbitration
and compels arbitration when there is a written agreement to
arbitrate.
… and an order that denies a stay is a final
appealable order.
ORC §2711.02: As Ohio wants to encourage arbitration,
only an order that denies a stay (pending arbitration) is
appealable; an order compelling arbitration is not appealable.
Thou
shall sue in Ohio (on Ohio projects).
O.R.C. §4113.62(D)(2): Disputes concerning Ohio construction
projects are only supposed to be litigated in Ohio courts.
Thou shall apply Ohio law.
O.R.C. §4113.62(D)(1): Ohio law is to apply to Ohio
construction projects regardless of the choice of law provision
in the contract.
Thou shall not waive bond rights.
O.R.C. §4113.62(A): In Ohio, one cannot waive bond rights "up
front" in a contract.
In short, Ohio has much law restricting "freedom of contract" in
the construction industry in an effort to avoid inequitable contracting
practices.
Ohio's Reform Effort
(House Bill 208) Passes Committee
In a seven to one vote on December 9, 2003, the House Commerce
and Labor Committee approved the Retainage Reform Bill (Sub.
H.B. 208), that follows the lead of the Federal Government
and the Ohio Department of Transportation, who have eliminated
retainage. While the Bill does not eliminate retainage in its
entirety, it radically reforms retainage practices in the State
of Ohio on both public and private commercial work in the following
respects:
Retainage would be capped at a maximum of 2%;
There
would be line item release of retainage by trade when that
trade's work is fully complete;
Owners would have to
pay their bills within twenty days of approval of the draw
request, granting of a certificate of occupancy,
or expiration of a trade's lien rights, whichever occurs
first, or would be liable for 18% interest and attorney's
fees;
There could be no improper or excessive "hold backs" in
the form of retainage or otherwise, such as excessive amounts
withheld for operating manuals, warranties and the like; and
Interest would be paid on retainage at all levels of
the "construction
food chain."
Supporters of the bill believe that it will speed up payment
and reduce the impact of using contractors and subcontractors
as "the bank," while at the same time not sacrificing
quality or timeliness of work. Don
Gregory and Dan
Hilson were
actively involved in the drafting and passage of the bill out
of Committee on behalf of Ohio's subcontractors. The bill
is currently awaiting a possible vote by the entire House of
Representatives. Anyone with opinions on the merits of this Retainage
Reform Bill (H.B. 208) should contact their State Representative
or Senator to communicate their thoughts on the bill as currently
drafted.
Dramatic recent construction material escalation costs, particularly
in steel, have created hardship for many in the industry and
caused some contractors, subcontractors and suppliers to consider
placing a condition in their bid proposal or contract protecting
the bidder from these costs, such as:
"In the event of significant delay or price increase
of material, equipment, or energy occurring during the performance
of the contract through no fault of the contractor, the contract
sum, time of completion, or contract requirements shall be
equitably
adjusted by change order in accordance with the procedures
of the contract documents. A change in price of an item of
material,
equipment, or energy will be considered significant when
the price of an item increases ____ percent between the date
of this
contract and the date of installation."
While such a clause could be readily utilized on negotiated
private work, there is considerable doubt that such an escalation
clause could be used on public work where a bid must be responsive
to the bid solicitation. It remains uncertain whether a differing
condition or equitable adjustment clause could be utilized on
public work to support an unexpected material cost increase.
Forum Selection Clauses v. State Statutes Prohibiting Such Clauses
Many states (including Ohio) have recently enacted statutes
that require construction-related litigation be conducted in
the state where the project is located. Many construction contracts
contain forum selection clauses requiring that the drafter's
state law apply and that litigation must be commenced in a state
far from the construction project. Both forum selection clauses
and the number of states passing statutes restricting the use
of forum selection clauses in construction cases (and mandating
litigation where the project is located) are on the rise. Complicated
legal issues can be involved when the two are juxtaposed.
The general issue was addressed by the landmark U.S. Supreme
Court case of The Bremen et al. v. Zapata Off-Shore Co., 407
U.S. 1 (1972), where the Court explained that if the forum selection
clause violates public policy, then the forum selection clause
must give way. However, in cases interpreting the Miller Act,
which mandates that federal public projects be brought in the
judicial district where the contract was performed "and
not elsewhere," courts have upheld the forum selection
clauses in the contract and not the Miller Act's jurisdictional
provisions.
Accordingly, the key issue is whether the state and federal
courts will enforce the state statutes or defer to the contract.
Two
recent cases have dealt with this issue. In Florida, in Kerr
Construction, Inc. v. Peters Contracting, Inc., 767 So.2d 610
(Fla. 5th DCA 2000), the court invalidated a venue selection
clause in a case that involved a Florida construction project
with a venue selection provision requiring litigation in another
state. The Florida court invalidated the contract provision based
upon Florida's construction jurisdictional statute. In
McCloud Construction, Inc. v. Home Depot U.S.A., Inc., 149 F.Supp.2d
695 (E.D. Wis. 2001), the federal court threw out a forum selection
clause requiring litigation in Georgia based upon Wisconsin's
public policy prohibiting forum selection clauses requiring litigation
in another state. Nevertheless, there is some risk that when
an owner or contractor files first in the state where the contract
says the dispute should be heard that the Court will find the "home
rule statute" inapplicable.
Therefore, contractors and subcontractors should not presume
that contract language (mandating that another state's
law or courts apply) is unenforceable and should instead strike
such language and require application of the courts and law where
the project is located.
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by Donald W. Gregory for the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.