In an important case for construction companies doing business
in Ohio, the Ohio Supreme Court recently vacated a Franklin County
Court of Appeals decision and reinstated an administrative decision
finding that a company is not liable for violation of any specific
safety requirements.
In State, ex rel. Mahoney v. Team America III and Wanner
Metal Worx, the general contractor, Sherman Smoot Company,
subcontracted work on the renovation of the future Supreme
Court building in downtown Columbus to Wanner Metal Worx. Smoot
had erected two scaffolds on the outside of the building, adjacent
to each other, with one being four to six floors above the
other. Smoot employees were working on the upper scaffold while
Mahoney, who was working for Team America, a staff leasing
agency for Wanner, was working on the lower scaffold. He was
injured when a piece of stone, chipped off the side of the
building by an employee on the upper scaffold, struck Mahoney
on the back of the neck. Mahoney's workers' compensation claim
was allowed against Team America. He then filed an application
for an additional award for violation of specific safety requirements,
known as a VSSR, against both Team America and Wanner.
A provision in the Ohio Constitution provides that an employee
who is injured in the course of his/her employment can request
a VSSR award, which is a penalty levied against an employer if
it is found that the worker's injury occurred because of the
employer's violation of some specific safety requirement. These
safety requirements are typically found in the Ohio Administrative
Code. Mahoney cited provisions in the Administrative Code concerning
overhead protection, safety belts and lifelines, and protective
railings on scaffolds.
After the hearing, at which Dave
McCarty represented Wanner, the Industrial Commission denied
Mahoney's request for a VSSR award. First, it found that Wanner,
rather than Team America, would be liable for any VSSR because
Wanner actually supervised and controlled Mahoney's work. However,
it found no safety violation. The Commission found that Wanner
provided safety belts and lifelines and all of the open sides
of the scaffold were properly guarded. The Commission also
found that Wanner provided sufficient overhead protection for
Mahoney. Mahoney appealed the matter to the Franklin County
Court of Appeals. Though a Magistrate recommended denial of
Mahoney's appeal, a three judge panel of the appellate court
rejected that recommendation and found that Wanner did not
provide overhead protection. Wanner then appealed the matter
to the Ohio Supreme Court.
Dave McCarty represented
Wanner in the Supreme Court action and Don
Gregory represented the American Subcontractors' Association,
an amicus (friend of the court) party to the action.
After briefing and oral arguments, the Ohio Supreme Court agreed
with Wanner and reinstated the Industrial Commission's decision.
The Court first noted that, because a VSSR is a penalty, the
safety requirements must be strictly construed in favor of the
employer. The Court noted that the term "overhead protection" is
not defined in the Administrative Code. The Court then found
that the safety measures Wanner implemented were sufficient to
satisfy its obligation to provide overhead protection. The Court
found that Wanner satisfied that obligation when it:
provided Mahoney with a hard hat;
directed Smoot to erect a vertical plywood barrier at the
end of the upper scaffold adjacent to the near side of the
lower scaffold;
created a "safe zone" mandating that, when Smoot
employees were working on the adjacent side of the upper scaffold,
there was to be no work done on the near side of the lower
scaffold; and
it ensured that the upper scaffold had toe boards.
Mahoney urged the Court to find a violation because there was
no protection directly overhead of the workers.
The Court rejected that interpretation and found that the overhead
protection rule affords discretion to the employer to determine
the means by which to protect its employees. Finally, the Court
rejected Wanner's argument that, because Wanner is not a party
to the underlying workers' compensation claim with the ability
to contest it, Wanner's due process rights were violated.
This is a significant victory for employers in the construction
industry. Had the Supreme Court not reversed the Court of Appeals,
employers virtually would have struggled with uncertainty and
been compelled to drastically modify scaffolding to include roofing,
canopies and/or nets, at tremendous cost. The Supreme Court resisted
the apparent attempt by the Franklin County Court of Appeals
to "legislate from the bench" and create safety requirements
that simply are not contained in the Administrative Code.
Court Holds Notice of Commencement
Must Be in Substantial Compliance
What should a subcontractor or material supplier do when the
notice of commencement is deficient and contains incorrect information?
According to one appellate court, the subcontractor must still
follow all the statutory requirements and file a notice of furnishing
in order to preserve lien rights.
In Linworth Lumber Co. v. Z.L.H. Ltd. et al, the notice
of commencement contained incorrect information for several of
the mandatory requirements. The subcontractor asserted that a
faulty notice of commencement excused the requirement for filing
a notice of furnishing. The court of appeals disagreed. The court
reviewed the mechanics' lien statute and found the notice of
commencement requirements outlined in O.R.C. 1311.04 are ambiguous.
One section (1311.04(A)) requires the notice of commencement
to be "substantially the form specified" in contrast
to the strict compliance language of the very next section (1311.04(B))
which mandates that the notice of commencement "shall contain" the
twelve statutory requirements.
The court concluded that a notice of commencement must only
be in substantial (not strict) compliance. In
evaluating the inconsistency in the statute, the court indicated
that "the overriding purpose ... is to put subcontractors
or materialmen on notice of who the owner is and where the construction
work is to be done." According to the court, because changes
to the notice of commencement do not effect the effective date
of the notice of commencement then incorrect information must
not invalidate it either. Therefore, the court found the notice
of commencement "fulfilled the necessary requirements for
recording and put subcontractors or materialmen on notice the
information pertaining to the real property which was necessary
for the preparation of the notice of furnishing."
This case gives owners who make certain mistakes in the notice
of commencement a break. A subcontractor facing this situation
should still file a notice of furnishing because section 1311.04(C)
gives lien claimants the opportunity to correct a lien containing
wrong information obtained from a faulty notice of commencement
and maintain a damage claim against the owner.
Recently, the Ohio Supreme Court heard arguments on a case that
will determine the future effectiveness of Ohio's Prompt Pay
Act. The Prompt Pay Act assists subcontractors and material suppliers
in receiving timely payment for labor, materials, and equipment
supplied to a project and includes attorney fees and 18% interest
that can be assessed against contractors failing to pay within
10 days of receipt of money from an owner.
The Ohio Supreme Court is considering the case of Masiongale
Electrical-Mechanical, Inc. v. Construction One, Inc. from
the Franklin County Court of Appeals. In Masiongale,
the Supreme Court will evaluate the following statutory provision: "The
contractor may reduce the amount paid by any retainage provision
contained in the contract, invoice, or purchase order … and
may withhold amounts that may be necessary to resolve disputed
liens or claims involving the work or labor performed
or material furnished by the subcontractor."
The issue is what is a "disputed lien or claim." Subcontractors
seek a narrow definition that "disputed lien or claim" means
a mechanic's lien on a private commercial project or a claim
against the public funds on a public project. This provision
allows a contractor to withhold a subcontractor's pay until the
subcontractor addresses the outstanding lien or claim from a
lower-tier subcontractor or material supplier. Contractors seek
a much broader definition of this language to include back charges,
delay claims, or claims for defective work. The effectiveness
of the Prompt Pay Act may depend on how the Courts define this
term.
In Masiongale, the contractor asserted that the Prompt
Pay Act allows him to withhold from the subcontractor's pay the
necessary funds to resolve other disputes including the cost
of bonding off a mechanic's lien and the potential cost of defending
the lawsuit out of state.
In evaluating the definition of liens and claims, the Court
of Appeals concluded definitively as a matter of law, that the
Prompt Pay Act does not allow a withholding for actual or potential
litigation costs or for premiums paid to bond off mechanic's
liens. The Court explained that a contractor can only withhold
pay that "may be necessary to resolve disputed liens or
claims involving the work or labor performed." The
Court noted that the "intent of the Prompt Payment Act is
exactly that—to encourage contractors to promptly pay their
subcontractors." The Court added that in recognizing that "disputes
do arise over such things as the quality of the work performed
or materials used, … the legislature provided for the withholding
of amounts related to such disputes." The Court concluded
that "the proper interpretation of the statute is that a
contractor may withhold amounts that are directly related to
alleged faulty work, labor or materials[; however, a]ncillary
costs that may arise as a result of such disputes, such as actual
or potential litigation costs, cannot be withheld, as these costs
are seldom definite and, more often than not (and certainly in
the case of potential litigation costs), will greatly exceed
the direct amounts disputed."
The Ohio Supreme Court will now decide how narrowly to define
this "excuse" for lack of prompt payment.
In November, Mike Copley made a presentation to the American
Subcontractors Association-Central Ohio Chapter on "Mold" and Don
Gregory taught "Fundamentals of Construction Law" sponsored
by the Construction Forum of the American Bar Association.
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by Donald W. Gregory for the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.