Recently the Franklin County Court of Appeals upheld a trial
court's landmark ruling that the State had considerable discretion
in awarding public contracts to contractors other than the low
bidder.
O.R.C. §153.08 provides that the State will award public
works projects to the "lowest, responsive and responsible" bidder.
O.R.C. §9.312 sets forth the criteria that are to be considered
when determining whether a bidder is "responsible" for
that project, including the experience, management skills and
financial resources of the bidder, but this provision has been
infrequently applied by public authorities. In a landmark case
last year construing these "responsibility" provisions,
Judge Sheward of the Franklin County Common Pleas Court ruled
that Cleveland Construction, Inc., while low bidder, was not "responsible" to
perform the sizable general trades portion of the Max Fisher
Business College project for The Ohio State University, and upheld
the award to the second low bidder, Danis Building Construction
Company.
The Trial Court rejected the low bidder's contentions that the
public officials had abused their discretion in the investigation
and evaluation process and further that there were technical
defects in the "responsibility" process applied by
the State.
The Trial Court went on to uphold the constitutionality of the
process and affirmatively ruled that it was fair and reasonable.
The low bidder appealed the case to the Franklin County Court
of Appeals, who on June 10, 1997, affirmed the Trial Court's
decision in all respects. The three judge appellate panel ruled
unanimously that:
The State did not apply "unannounced criteria" to
the responsibility determination, particularly where, as
here, the same criteria was applied to all bidders.
The State did not improperly "compare" the bidders
simply because all of the information relative to responsibility
was obtained from all the bidders at the same time due
to the limited time available.
The duty to assess the responsibility determination may
be delegated by the Deputy Director of the Department of
Administrative Services.
The State has the discretion to refuse to award a contract
to the low bidder if it is not in the best interest of
the State.
The State need not promulgate rules for the responsibility
process nor must the low bidder be given the right to due
process —such as cross-examining witnesses at the
bid protest meeting.
The responsibility process, as applied by the State here,
was constitutional.
This decision upholding the "responsibility" evaluation
process will likely encourage more frequent use of the statute
by public owners in the future, with the result being that the
low bidder may not always be the successful bidder.
When Are "No Damage for Delay" Provisions
Enforceable?
As everyone associated with the construction industry knows,
on any construction project "time is money." In view
of increasing construction claims, more owners and contractors
are attempting to draft no damage for delay provisions in their
contracts and subcontracts respectively to help insulate themselves
from additional expense on projects where completion is delayed.
Generally, no damage for delay ("NDFD") provisions
will be strictly construed. In applying the most common exception,
a court will look to see if the specific delays encountered were
of the type that would be within the contemplation of the parties
at the time the contract was entered into. If the specific delay
at issue is of the type that would not be within the contemplation
of the parties when the contract was made, then the clause will
not serve to preclude the award of damages to the contractor
for the delay.
Delays Not Contemplated by Parties at
the Time of Contract Are Not Within the Scope of a "No Damage
for Delay" Clause.
In Nix, Inc. v. City of Columbus, 171 N.E.2d 197 (Ohio
App. 10th Dist. 1959), the contractor entered into a contract
with the City of Columbus on the assumption (by both parties)
that the city had procured the necessary right of way for the
project. In fact, the city did not have the necessary right of
way and the project was delayed by four months as a result. The "no
damage for delay" clause at issue was very broad and included
damages for "any hindrance or delay from any cause whatever
in the progress of the work." The court held that damages
arising out of the city's delay in acquiring the right of way
were not precluded by the no damage for delay cause. The court
explained that where both parties had signed a contract on the
assumption that the city had acquired the right of way, any damages
resulting from the city's delay in attaining the right of way
were not within the contemplation of the parties at the time
the contract was made.
This rule also applies to the State on public projects. In Royal
Elec. Constr. Corp. v. The Ohio State Univ., 1993 WL 532013,
at *1, the contractor was delayed in starting on the project
as a result of the unexpected discovery of asbestos and other
problems. First, the provision in issue provided that "there
is no liability for damages resulting from delay caused by
third persons." The court, by strictly construing the
provisions found that the provision did not apply to delays
caused by the State because the State was not a "third
person."
Next, the court found that even if the provision applied to
the parties it would not have applied to the specific delays
experienced by the contractor. The court found that the delays
encountered by the contractor "were well beyond what could
have reasonably been anticipated by the contract" and further
noted that the "discovery of asbestos in flooring and pipes
was unanticipated, and that the delays by the general contractor
and others led to an accumulation of delays that resulted in
the loss of an unreasonable amount of time." The court went
on to state that "a certain amount of delay in a construction
project may be foreseeable, the accumulation of delays can be
of such a magnitude that, taken together, the extent of delay
becomes unforeseeable." The court concluded by finding that
because the delays experienced by the contractor "were unforeseeable,
the delays necessarily were 'not within the contemplation of
the parties at the time the contract was made'", and thus,
it would have been proper for the lower court to refuse to enforce
an otherwise valid no damage for delay clause.
In Avon Excavating Co. v. City of Parma, supra, LEXIS
41557, at *1, the contractor alleged that the bid plans were
prepared incorrectly and that the city interfered with the construction
of the project, that it ordered unauthorized work stoppages and
that it failed to timely acquire and deliver easements so that
the contractor could proceed in a timely manner. The trial court
put the issue to the jury to determine whether or not the delays
were in the reasonable contemplation of the parties at the time
the contract was entered into. The jury found that the delays
were not within the contemplation of the parties and thus awarded
damages. The court of appeals upheld the decision.
In the most recent case on the subject, the Franklin County
Court of Appeals reversed the summary judgment in favor of the
public owner and held that for a NDFD provision to be enforceable,
the extent and magnitude of the delay must have been foreseeable. Cleveland
Construction v. Reynoldsburg City Schools, Case No. 96APE02-242
(June 28, 1996, unreported). A prime contractor defaulted and
it took the School District a significant amount of time to replace
the defaulting contractor, causing delay to the project and damage
to the other prime contractors. The Court of Appeals ruled that
the trial court had erred by ignoring the case law and granting
summary judgment for the School District with a literal reading
of the NDFD clause. The Court of Appeals reversed because a NDFD
clause is not enforceable when the magnitude of the delays was
unforeseeable.
Another recent case from the Northern District of Ohio held
a NDFD clause unenforceable when the owner failed to keep its
promise to effectively supervise and coordinate the work of the
other prime contractors. JWP/Hyre Electric Co. v. Mentor
Village School District, 1996 U.S. Dist. LEXIS 2117 (February
9, 1996).
Claims for Hindrance or Obstruction Are
Not Barred by a "No Damage for Delay" Clause.
The Sixth Circuit in John E. Green Plumbing v. Turner Construction
Co., 742 F.2d 965 (6th Cir. 1984), in determining whether
or not the clause applied to the facts of that case, made an
important distinction between the terms hindrance and delay.
In the Green case, the clause at issue forbade damages
resulting from the contractor being "delayed in the commencement,
prosecution, or completion of the project." The clause
made no mention of "hindrance" and thus Green argued
that the clause, "strictly construed, only bars delay
damages and not other kinds of damages, such as damages for
hindering work on the project." The court agreed with
Green and went on to define delay as meaning "time lost
where work cannot be performed because essential supplies have
not been delivered or necessary preliminary work has not been
performed." Thus, the court concluded that delay damages "refers
simply to the cost of an idle workforce."
Applied to the facts of that case, the NDFD clause did not apply
where the contractor suffered damages from obstacles created
by the construction manager. Examples include, the construction
manager allowing another contractor to brick up an area that
Green needed access to and failure of the manager to ensure that
temporary heat was provided. Thus, an action for damages arising
out of hindrances and obstructions created by the construction
manager (as opposed to delays) was not precluded by the NDFD
provision that only addressed "delay."
NDFD provisions place contractors at risk that they will be
unable to recover damages for delay, even if caused through no
fault of their own, but whether a NDFD provision is legally effective
will likely hinge on the particular facts of that case.
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by Donald W. Gregory for the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.