Our firm was recently involved with probably the first case in
Ohio to interpret whether, under the Ohio's Modern Mechanic's Lien
Law, a defective Notice of Commencement ("NOC") excuses
a subcontractor or supplier from the duty to serve or attempt to
serve a Notice of Furnishing ("NOF") upon the owner.
Prior to this decision, many commentators believed that even technical
flaws in a recorded Notice of Commencement did not excuse a subcontractor
or supplier from attempting to serve a Notice of Furnishing.
However, in the case of RN Building Materials v. Ahn,
Judge Travis of the Franklin County Common Pleas Court ruled that
several significant procedural defects in a layman prepared Notice
of Commencement (no legal description, wrong owner name) excused
a supplier from its obligation to serve a Notice of Furnishing,
even when the supplier made no attempt to serve such a Notice.
This means that owners must take special care in seeing that Notices
of Commencement are properly prepared, filed with the county recorder
and kept posted on the jobsite. This case also gives subcontractors
and suppliers an opportunity to salvage lien rights when they have
failed to serve a Notice of Furnishing, by later spotting technical "defects" in
the Notice of Commencement.
State Loses Another Delay Claim in the Court
of Claims
In the case of Field & Associates, Inc. v. Department
of Administrative Services, our firm successfully represented
the prime roofing contractor in a differing site condition claim
against the State due to greater thickness and hardness of the
existing roofing material to be removed. Judge Shoemaker of the
Court of Claims granted a judgment that included an amount for
the differing condition claim that was approximately half of
the original contract amount and withdrew the assessment of all
liquidated damages assessed by the State. He also granted the
contractor prejudgment interest in the amount of 10% per annum
from substantial completion of the project.
In the decision, Judge Shoemaker reinforced the
pro-contractor case law established in the Court of Claims following
the Valentine case years ago, including the principles
that:
ambiguities in the contract documents are to be construed
against the State;
constructive notice of a change or differing condition is
adequate to satisfy the notice provisions of the State's
contract;
a contractor is entitled to an equitable adjustment for
any conditions that could not have been discovered in a reasonable
site inspection; and
a contractor is entitled to any extra costs incurred as
a result of any errors or omissions in the plans and specifications.
Judge Refuses to Enjoin Demolition of the
Ohio Pen
Judge Hogan of the Franklin County Common Pleas Court denied
an injunction to a disgruntled bidder on the Ohio Penitentiary
demolition project and upheld the award of the contract to our
client S.G. Loewendick & Sons, Inc., allowing the demolition
to proceed. The Court specifically found that there was no evidence
that the plaintiff would suffer irreparable harm if the temporary
restraining order were not granted.
In a sudden move surprising to many in the construction industry,
the Ohio General Assembly recently passed Am. Sub. Senate Bill
102 which will exempt from prevailing wages all construction undertaken
by school districts and educational service centers effective August
18, 1997. Ron Mason of our firm was heavily involved with the legislation
on behalf of ABC.
The Ohio Supreme Court has ruled that a contractor who removed
additional hazardous material on a unit price basis without a written
change order did so at its own peril and denied recovery for almost
a million dollars of extra work. Foster Wheeler Enviresponse
v. Franklin County Convention Facilities Auth. (1997), 78
Ohio St. 3d 353. The contractor had agreed to remove a certain
quantity of contaminated soil for the public authority. Additional
quantities over and above the base bid were to be paid on a unit
price basis, but the public authority maintained that increases
in the quantity of work were an alteration in the scope of work
that required a written change order. The Supreme Court agreed,
despite the fact that the public authority knew that additional
quantities were being removed and its consultant was allegedly "signing
off" on the measurements of soil removed. This case emphasizes
the dire consequences to contractors that can occur when the written
change order requirements are not strictly complied with before
performing the extra work.
Senate Reintroduces Fairness in Construction
Contracting Bill as S.B. 71
Senator Cupp has reintroduced the Fairness in Construction Contracting
Bill (S.B. 71). This legislation initially began as an effort to
bar "pay-if-paid" contract language which prevents construction
subcontractors who perform satisfactory work from being paid when
an owner, for whatever reason, fails to pay the general contractor.
There was some initial opposition to this bill from general contractors.
This bill was originally introduced in March of 1995 as S.B. 106
(now S.B. 71). At the request of the sponsor, the construction
industry representatives held several meetings and negotiated their
differences.
After extensive discussion, negotiation and drafting, the general
contractors of the State represented by AGC-Ohio and the subcontractors
represented by the Ohio Subcontractors Council have reached agreement
on a compromise and consensus industry bill - Sub. S.B. 71 (Fairness
in Construction Contracting Bill).
This legislation is designed to remedy certain inequities in construction
contracting created by adverse court decisions or unfair practices
within the industry, and contains the following elements:
Requires subcontractors and suppliers to provide a
Notice of Furnishing to preserve bond rights (as is the current
law for mechanic's lien rights). This will prevent "hidden
bond claims" and make bond claims consistent with mechanic's
lien claims.
Clarifies the existing anti-indemnity statute to provide
that one cannot force another to pay the attorney's fees
and costs arising from a person's own negligence. This
will eliminate the inconsistency of making one pay the negligent
party's attorney's fees when the existing statute
makes it clear the non-negligent party cannot be required
to pay for the personal injury or property damage caused
by the negligent party.
Prohibits as against public policy:
a. waiving bond rights by contract without payment;
b. waiving pending claims by final payment; and
c. "no damage for delay clauses" (when
the owner or contractor causes the delay).
This will prevent one from inadvertently giving up important
legal rights by virtue of one-sided contract language hidden
in the fine print of lengthy non-negotiable construction contracts.
Allows subcontractors and suppliers to file mechanic's
lien and bond claims within the deadlines provided by law,
despite the existence of contingent payment clauses. This
will prevent "pay-if-paid" clauses from interfering
with the filing of lien and bond claims which are necessary
to secure payment.
These provisions should cause a more equitable sharing of risk
in the construction process by encouraging the party most able
to manage or control that risk to remain responsible for it.
While there has been some concern expressed by certain utilities
and the State with regard to two features of the bill, it passed
the Senate 32-1 during the last session, but ran out of time before
a vote could be taken in the House of Representatives. The goal
of the construction industry is to move the bill through the legislature
before the conclusion of this session. If enacted into law, it
will dramatically change construction contracting here in Ohio.
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by Donald W. Gregory for the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.