Many Central Ohio subcontractors were denied recovery of their
payment bond claims against the bonding company after the general
contractor became insolvent, because they signed subcontracts
containing a provision purporting to waive payment bond rights.
The relevant subcontract language provided "subcontractor
waives and relinquishes any rights to pursue a claim on the surety
bond issued by contractor and its surety in connection with this
project." This problem raised the novel issue whether such
a waiver of payment bond rights, at the time of contract and
without payment, was enforceable under Ohio law.
As there was no legal authority on point in Ohio, the bonding
company filed suit seeking a declaration that such a subcontract
provision was enforceable and that the subcontractor's claims
should be denied under "freedom of contract." The subcontractors
argued that such a provision violated public policy, as well
as Ohio's bond statutes, and should be declared unenforceable.
The subcontractors argued that if such subcontract "fine
print" were effective then the public owners of the State
would suffer as well as the subcontractors, in that the owner
(and indirectly the taxpayers) will have paid for a bond that
did not serve its intended purpose of ensuring payment to subcontractors,
which is not only inherently beneficial, but encourages subcontractors
to bid and perform public construction work at the lowest possible
price. It also could lead to the undesirable result of having
unscrupulous contractors place this language in their subcontracts,
lowering their risk, and achieving an unfair competitive advantage
over contractors who use equitable contract language and expect
to pay their bills to subcontractors.
In a landmark victory for local subcontractors, Judge Cain of
the Franklin County Common Pleas Court in the Farrell Construction
case agreed with the subcontractors and ruled that the subcontract
waiver language conflicted with Ohio's bond statutes and was
unenforceable for that reason. This decision should allow the
subcontractors in the case to recover on their bond claims and
discourage the use of such language in the future.
In addition, there is legislation pending in the Ohio General
Assembly that would specifically find such "waiver of bond
rights" language to be unenforceable and against public
policy in Ohio.
Until such a bill becomes law in Ohio, prudent subcontractors
will want to closely review their subcontracts and consider objecting
to any provisions that purport to waive bond rights without full
payment.
OEPA Adopts Rules for Disposal of "Construction & Demolition
Waste"
If you do construction or demolition work in Ohio, you may want
to take a look at the new Ohio Environmental Protection Agency
("OEPA") rules that went into effect on September 30,
1996 regarding the disposal of construction and demolition waste.
These new rules, codified at chapters 3745-37 and 3745-400 of
the Ohio Administrative Code, supersede any county regulations
that previously regulated construction and demolition ("C & D")
landfills.
Generally, the new rules define "construction and demolition
waste" as those materials resulting from the alteration,
construction or destruction of any man-made physical structure.
Contractors throughout the state will be required to dispose
of construction and demolition debris only at approved C & D
sites or solid waste disposal facilities. Examples of acceptable
C & D waste materials include: shingles, roofing paper, drywall,
plaster, studs, joists, rafters, electrical wiring, plumbing
fixtures, heating equipment, cement block, cabinets, glass, window
frames, and structural metal and wall coverings. Also, if incidental
to the load, construction material packaging such as pallets,
cardboard and empty caulking tubes are acceptable C & D fill
materials.
Materials that may not be disposed of at C & D fills include
those materials that were required to be removed prior to demolition,
and materials which are otherwise contained within or exist outside
the structure. Such items include yard wastes, furniture, appliances,
tires, batteries, garbage, and other solid waste.
An important exception to the rules relates to the disposal
of "clean hard fill." OEPA defines clean hard fill
as construction and demolition debris which consists of only
concrete, asphalt, brick, block, tile, stone, and mortar. In
essence, if the contractor can separate out the wood and unacceptable
materials from the pile, this clean hard fill can be used to
change grade at the demolition site. In addition, this material
can also be used to change the grade of another site provided
that a written "notice of intent to fill " is submitted
to the local health department in the county where the fill is
to be used. Although, clean hard fill can be stored for two years,
this material should be covered with dirt if used to permanently
change grade.
Two approved construction and demolition landfills exist in
the Columbus area including the Central Ohio Contractors Inc.
("C.O.C.") facility located at 900 Frank Road.
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by Donald W. Gregory for the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.