In a hotly contested dispute arising over the settlement of the
Tolles Technical Center's expansion in Madison County, the School
District Owner sued the Contractor, Peterson Construction, and
excavation Subcontractor, George Igel & Co., alleging that
the construction team had failed to remove all of the organic soils
under the building to full depth. The contractors countered that
they had fully performed the work according to the specifications
and that the Soils Engineer retained by the Owner, Dunbar, was
responsible for any errors concerning the identification and removal
of organic soils.
This situation was complicated by the fact that the School District's
contract contained disclaimers purporting to disclaim any liability
for the subsurface reports or the actions of the soils engineer.
After a two week trial before Madison County jurors, all of whom
were taxpayers in the School District, the jury agreed with the
Contractors' position that they had fully complied with their contract
and subcontract obligations respectively, threw out the school's
claim in excess of $1 million and awarded the Contractors more
than $323,000 in excess costs advanced by them to help repair the
building.
As reported in a previous issue (May, 1996), Judge Watson of
the Franklin County Common Pleas Court threw out a contractor's
delay claim against the Reynoldsburg Schools, on summary judgment,
due to a "no damage for delay" provision, even though
the contractor had argued that the delays were not foreseeable
at the time of contracting. The matter was appealed and an amicus brief
filed by AGC-Ohio in support of the contractor's position.
On June 23, 1996, the Franklin County Court of Appeals reversed
Judge Watson's decision by ruling that the trial Court must determine
the extent and magnitude of the accumulation of delay and whether
or not this was foreseeable, before determining whether a "no
damage for delay" provision is enforceable. This appellate
decision is consistent with other Ohio law on the subject and gives
contractors and subcontractors an argument as to why a "no
damage for delay" provision should not bar their delay claim.
However, the best defense to a "no damage for delay" provision
is to refuse to bid such work or sign such a contract, or in the
alternative, to pass legislation making these provisions void as
against public policy.
Senate Passes Fairness in Construction Contracting
Bill
After extensive discussion, negotiation and drafting, the general
contractors of the State represented by AGC-Ohio and the subcontractors
represented by the Ohio Subcontractors Council (ASA) have reached
a compromise and consensus industry bill-Sub. S.B. 106.
The legislation is designed to remedy certain inequities in construction
contracting created by adverse court decisions or unfair practices
within the industry and contains the following elements:
Requires subcontractors and suppliers to provide a Notice
of Furnishing to preserve bond rights (as is the current
law for mechanic's lien rights).
Clarifies the existing anti-indemnity statute to provide
that one cannot force another to pay the attorney's fees
and costs arising from a person's own negligence.
Prohibits as against public policy:
waiving bond rights by contract without payment
waiving pending claims by final payment
"No damage for delay" clauses.
Allows subcontractors and suppliers to file mechanic's lien
and bond claims within the deadline provided by law, despite
the existence of contingent payment clauses.
These provisions should cause a more equitable sharing of risk
in the construction process rather than simply shift all risk to
the party least able to manage or control that risk, and as a result
create a fairer and more competitive construction marketplace,
ultimately benefiting all Ohioans.
The bill passed by a 32-1 margin in the Senate on May 28, 1996
and is now pending in the House of Representatives.
Columbus Set-Aside Policy Ruled Unconstitutional
Again
Judge Graham of the U.S. District Court, Southern District of
Ohio, has recently ruled in a 237 page opinion that the City of
Columbus did not follow a pattern of discrimination in its minority
contracting and therefore its minority contracting set-aside policy
is unconstitutional. The City's policy had adopted goals of 10%
for minority owned businesses and 7% for women owned businesses.
Under the U.S. Supreme Court case of City of Richmond v. J.A.
Croson Co., governments attempting to implement set-aside
programs must prove that discrimination occurred by that governmental
body. Judge Graham ruled the City of Columbus was unable to prove
that such discrimination against minority and female contractors
occurred by the City of Columbus. It is uncertain at this point
whether the City will appeal.
Subcontractors and suppliers suffered a legal setback when the
Ohio Supreme Court ruled in the case of LaPuma v. Collinwood
Concrete, 75 Ohio St.3d 64 (1996), that a homeowner could
still sue a concrete supplier directly despite having no contract
with the supplier. In that case, the homeowner complained that
the driveway was the wrong color and sued the supplier in tort
for a breach of the implied warranty of workmanship. Despite having
no contract directly with the homeowner, the Ohio Supreme Court
held that the supplier could be sued directly for damages to the
product itself, here the concrete driveway. This means that subcontractors,
suppliers and other providers of construction services, without
privity of contract with the owner, will be increasingly targets
for lawsuits when the contractor is irresponsible or uncollectible.
The Jefferson County Court of Appeals ruled that a mandatory
project labor agreement, which imposed uniform procedures for dealing
with labor disputes and working conditions did not violate the
public bidding statutes or the state equal protection clause where
no bidder was prevented from submitting a bid and there was allegedly
no distinction between union and nonunion contractors. State
ex rel. ABC v. Jefferson Cty. Bd. (1995), 106 Ohio App. 3d
176.
Contractor May Be Liable to Sub's Employees
for Prevailing Wages
The Franklin County Court of Appeals in the case of Connell
v. Wayne Builders, Case No. 95APE07-897, has ruled that
a subcontractor's employees, as third party beneficiaries to
the prime contract requiring the general contractor and all subcontractors
to pay prevailing wages, may sue a general contractor to recover
unpaid wages after the state has determined that a violation
of the wage and hour laws has occurred.
Patrick O'Neill, who has worked in the construction industry,
has joined the firm to work exclusively in the Construction
Law area. Don
Gregory successfully represented Igel in the Tolles case
and helped draft and pass Sub. S.B. 106 on
behalf of ASA.
Ron Mason argued the Jefferson County project agreement case for
ABC. Mike Galeano has been named as a director of the firm.
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by Donald W. Gregory for the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.