"Pay When Paid" subcontract agreements are structured
in a way that payment from the general contractor to the subcontractor
is conditioned upon prior receipt of payment from the owner to
the general contractor. Ordinarily, the subcontract will state
that payment is due to the subcontractor within a certain period
of time after receipt by the general contractor of payment from
the owner. Such a conditioning of payment in a subcontract is
known as a "Pay When Paid" clause.
Ohio courts have traditionally interpreted "Pay When Paid" provisions
as an unconditional promise to pay, with the time of payment
being postponed until the happening of a certain event, or after
a reasonable period of time has elapsed if such event does not
take place. Thomas J. Dyer Co. v. Bishop Int's
Eng'g Co., (C.A. 6, 1962), 303 F.2d 655. That means that
the general contractor must pay within a "reasonable time" if
the triggering event does not occur —not that the general
contractor need not ever pay the subcontractor in the event of
non-payment by the owner.
However, recently many general contractors have begun inserting "Pay
If Paid" provisions in their subcontracts, stating something
to the effect that the subcontractor assumes the risk of non-payment
by the owner and payment by the owner to the general contractor
is a condition precedent to payment by the general contractor
to the subcontractor. In this way, the general contractor is
attempting to insulate himself from any liability to the subcontractor
at any time in the event of non-payment by the owner.
Court decisions in other states have upheld the validity of "Pay
If Paid" provisions if they unambiguously express the intention
of the parties to shift the credit risk to the subcontractor. Southern
States Masonry v. J.A. Jones Construction, (LA. 1987),
507 So. 2d 198, 206; Gulf Construction v.
Self, (Tex. App. 13 Dist. 1984) 676 S.W.2d 624, 627; Statesville
Roofing & Heating v. Duncan, (W.D.N.C. 1988), 702
F. Supp. 118, 121. Although no Ohio court in a reported case
has yet ruled on such a "Pay If Paid" provision, it
is likely that it would be found enforceable in view of the decision
in the Dyer case if it clearly stated that the credit risk of
the possible insolvency of the owner was being transferred from
the general contractor to the subcontractor.
However, the New York District Court for the Southern District
of New York recently found that such a "Pay if Paid" clause
in Gilbane's subcontracts was unenforceable under New York law
on a project where a payment bond was provided. This case has
been appealed and is being closely watched by the industry.
Both general contractors and subcontractors must pay particular
attention to the wording of these contingent payment provisions.
The Ohio Department of Transportation ("ODOT") is
in the process of instituting a new claims process through the
imposition of a new specification - Section 105.17. Pursuant
to this new claims procedure, contractors will have to give the
Engineer early written notice of the claim. Once the Engineer
responds in writing, the contractor has ten (10) days to submit
a notice of claim with the basis and nature of claim, or is deemed
to waive the claim. Within ten (10) days of the notice of claim,
the Contractor is to give the Engineer the estimated additional
time and cost of the claim or is deemed to have waived the claim.
No later than sixty (60) days after substantially all of the
Contractor's costs are known, the Contractor is to submit a detailed
claim to the Engineer, or again the claim is waived. The Engineer
is to then decide the claim within sixty (60) days after submission.
If the Contractor is unsatisfied with the Engineer's decision,
he must appeal to a newly created Director's Claim Board within
twenty (20) days who shall make a decision, in most cases, within
thirty (30) days after the hearing. Only after the Claim Board
decision can the Contractor file suit in the Court of Claims.
The time and notice restraints of this new procedure provide
significant procedural traps for unwary highway Contractors.
Under Ohio law, there is considerable confusion as to what
period of time a person has to file suit (the "statute of
limitations") for construction defects. In Drater
v. Willard Constr. Co. (1994), 93 Ohio App.3d 443, the
Court of Appeals for Lorain County struggled with this issue
and found that the owner had only:
Two years from the date the claim arose for damage to personal
property; and
Four years from the date the claim arose for damage to real
estate to file a lawsuit, even if the suit was filed timely
within Ohio's 10 year "statute of repose."
In a case favorable to bonding companies and unfavorable to
contractors or subcontractors providing bonds, the Court of Appeals
for Hamilton County held that a surety had no obligation to mitigate
its principal's damages under an indemnity agreement by attempting
to collect payment for work performed prior to the principal/contractor's
default. Four Seasons Environmental v. Westfield (1994),
93 Ohio App.3d 157.
This case gives bonding companies considerable latitude in deciding
what action to take or not when a contractor defaults, while
still retaining the ability to recoup its loss from the contractor
and its owners who signed the indemnity agreement.
There are several forms of subcontracts commonly used by general
contractors and subcontractors in the construction industry.
Starting with the most favorable to subcontractors and moving
to the least favorable would be:
AIA A401 - Endorsed by
ASA, but has never been accepted by AGC. Envisions important
role but little liability exposure for architect.
AGC 640/ASA 4100/ASC 52 -
Endorsed by all 3 of these organizations, it is a reasonable
compromise between contractor and subcontractor interests.
AGC 600 - This subcontract
formerly endorsed by AGC, has never been accepted by ASA.
Proprietary forms - These
in-house proprietary forms are typically used by large general
contractors whenever possible and are generally the least
favorable to subcontractors.
A summary of the key components of the three generally accepted
trade association subcontracts is as follows:
7 days after receipt from
owner but no later than resonable time
7 days after receipt from
owner
Contingent payment
Yes, but paid upon demand
if delay not caused by sub (11.3)
Yes - "Pay when paid" but
no later than "resonable time" (14.2.7)
Yes - "Pay when paid" (5.2.5)
Changes
Promptly or not less than
two working days preceding contractor's deadline (5.3)
Written notice by sub within
7 days of event (13.2.3)
Written notice by sub within
5 days of event (6.3)
Incorporation of prime
contract
Both parties bound by prime
contract (2.1, 16.1.2)
Subcontract controls (2.1)
May be listed to incorporate
by reference (3.1)
Subcontract controls (3.2)
May be listed to incorporate
by reference (2.2, 16.5)
Subcontract controls (2.3)
No damage for delay
No, damages for delay not
precluded (A201 8.3.3)
No, damages for delay not
precluded (13.3.2)
Yes, sole remedy for delay
is time extension unless contractor recovers (6.4)
Indemnity
Sub indemnifies contractor
for his negligence in whole or in part (4.6.1)
Sub indemnifies contractor
for his negligence in whole or in part (12.1)
Sub indemnifies contractor
for his negligence in whole or in part (12.1)
Safety
Sub is to comply with contractor's
safety directions (4.3.1)
Sub shall stop work if PCP / asbestos encountered (4.3.3)
Sub to indemnify contractor
for fines due to sub's safety failure on this job (9.14.9)
Sub shall stop work if PCP / asbestos / hazardous substances
encountered (9.17.1)
Sub is to follow contractor's
safety directions (8.7)
Lien waivers
Not specifically referenced
No unconditional lien waivers
prior to payment (14.2.2)
May submit conditional
lien waivers (5.1.5)
Mediation
Not required
Suggested (15.1)
Not required
Arbitration
Yes, AAA arbitration mandatory
(6.1)
Yes, AAA arbitration mandatory
(15.2)
Yes, AAA arbitration mandatory
(14.1)
Attorney's fees
None
To prevailing party in
suit or arbitration (7.4)
To prevailing party in
suit or arbitration (15.4)
*All cites refer to sections in form contract except those marked A201 which refers to A201 general conditions which may be incorporated into the AIA 401.
A constant source of disagreement between owners, contractors
and subcontractors is entitlement and amount of change orders.
The following issues need to be kept in mind from the initial
contractual negotiations through to contract close-out.
What does the contract provide with respect to advance notice,
in writing, etc.?
Can you be forced to perform extra work without an agreement?
Who has the authority to sign a change order?
Are you, if a subcontractor, limited to the contractor's
remedies against the owner?
By receipt of a change order, have you closed out any delay
claims for the cumulative effect of multiple changes?
Asbestos Abatement Contractor Not Liable
When Owner Sued by EPA
In a case of great concern to property owners and managers,
a trial court in Montgomery County has ruled in the case of Beerman
Realty Co., v. Alloyd Asbestos Abatement Co. (Case No.
93-3440) that an owner has no right to recover attorney's fees
and its EPA fine against a contractor who allegedly failed to
abate asbestos consistent with the Clean Air
Act. The Court ruled that each party was responsible for
its own attorney's fees and fines, and interestingly, that any
indemnity provision shifting this risk to the contractor would
be unenforceable. It is the latter position that is most troubling
to owners, who have traditionally attempted to shift the risk
of regulatory compliance to the person actually performing the
work by such an indemnity provision in the prime contract. The
case is currently on appeal.
It has become typical in the construction industry for prime
contract terms to be incorporated into subcontracts by reference,
thereby binding the subcontractor to the prime contractor's obligations.
This practice has been upheld by many courts recently, resulting
in occasional hardship to subcontractors. In a case out of Mississippi,
the appellate court determined that when the owner made final
payment to the contractor, the subcontractor's claims were also
released because of a provision in the prime contract (incorporated
into the subcontract by reference) which stated that final payment
to the prime contractor constituted a release of all claims.
In a case from Washington, the appellate court ruled that an
incorporation clause meant that a subcontractor was bound to
arbitration as a remedy if the prime contractor was bound to
arbitrate its disputes with the owner.
In view of these decisions, it is more important than ever for
subcontractors or suppliers to become familiar with the terms
of the prime contract governing the project.
Congratulations to Ted Scott and Jud Scheaf of
the Construction
Law Area who have become directors with the firm.
The net proceeds of the Construction/Labor Law Seminar held
in the Spring have been donated to the Columbus Housing Partnership,
a non-profit association providing housing for low income families.
Congratulations to Don
Gregory who was the only attorney named to Business
First's 1994 list of "Who's Who in Central Ohio
Construction, Architecture & Engineering."
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by Donald W. Gregory for the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.