In This Issue
Project Labor Agreement Barring Non-Union
Contractors Is Ruled Illegal
The Jefferson County Commissioners, who are going to build
a joint County/City of Steubenville Jail, required in the bid
documents that successful bidders sign a project labor agreement
with the local union. The Associated Builders and Contractors
and others, through Ron Mason of the firm, filed suit
challenging such a requirement and successfully argued that such
a mandatory labor agreement was illegal under Ohio's bidding
statues. The Court ruled that the Commissioners had to re-advertise
and rebid without such a requirement.
Back to Top
State Loses Another Appeal
The State's losing streak on construction claims cases that
have been appealed from its Court of Claims continues. In the
most recent case of Romanoff Electric v. Ohio
DAS, Case No. 1667, Franklin County Court of Appeals (June
30, 1994), the Court of Appeals sustained the decision of the
Court of Claims that it would have been futile for a contractor
to be required to dewater the site by pumping water into an inadequate
sewer that was backing up at the time. The Court of Claims had
previously ruled that the State knew the sewers were inadequate
and failed to inform the contractor, making the State liable
for breach of an implied warranty to provide the contractor with
a suitable site upon which to work.
The Court of Appeals also affirmed an award of prejudgment interest
against the State.
Back to Top
Asian-Indians Win State MBE Certification
In a decision that the State of Ohio has apparently decided
not to appeal, Judge Thompson of the Franklin County Common Pleas
Court has ruled that Asian-Indians meet the definition of "orientals" and
therefore qualify as a minority for the purposes of state contracts.
The Judge ordered the Department of Administrative Services
to recertify Asian-Indian companies who had been previously decertified
a year earlier.
Back to Top
No Claim for "Negligent Payment" Recognized
In an unusual case, a subcontractor filed suit against a tenant
for unpaid labor and materials, arguing that he had a claim for "negligent
payment" for the tenant's alleged failure to comply with
the mechanic's lien law in making payment to the general contractor. Henderson
Electric v. Elam Constr. Mgt. Serv. (1993), 92 Ohio App.
3d 98. The Court of Appeals for Hamilton County ruled that no
such independent cause of action exists for "negligent payment" and
denied recovery to the subcontractor.
Back to Top
Bonding Companies May Be Liable for Subcontractor's
Legal Fees
A case from California has held that a subcontractor may recover
attorney's fees from a bonding company when the subcontract provided
for an award of fees. T & R Painting v.
St. Paul Fire & Marine Ins. (Cal. App. 2d Distr. Div.
2, March 22, 1994) 1994 WL 90001. Now that the model ASA/AGC
subcontract provides for an award of attorney's fees to the prevailing
party, subcontractors may be able to recover their attorney's
fees against the bonding company even though the bond itself
does not specifically provide that it covers attorney's fees.
Subcontractors and suppliers in Ohio may be able to make a similar
argument that bonding companies are liable for 18% interest and
attorney's fees under Ohio Prompt Payment Act in that these amounts
constitute the "lawful claim" of the subcontractor
or supplier for which the bonding company is liable under the
terms of the bond.
Back to Top
Subcontractor Relieved from Bid
Due to Onerous Contract Terms
As a general principle, subcontractors are bound by their bids
to a general contractor when they are relied upon by the general,
even if a mistake has been made by the sub under the theories
of promissory estoppel or breach of contract. However, a recent
Nebraska case has carved out an important exception to this general
principle. Hawkins Constr. Co. v. Reiman Corp.,
245 Neb. 131, 511 N.W.2d 113 (1994).
In that case, the general contractor relied upon the subcontractor's
bid price and was the successful bidder. The general then sent
an onerous subcontract to the subcontractor, who objected to
many of its terms. When no agreement on contract language could
be reached, the general hired another sub at a higher price and
sued the original sub for the difference. The Supreme Court of
Nebraska ruled that because of the nonstandard and onerous terms
in the subcontract, there was no contract because there was no "meeting
of the minds" and the contractor's reliance upon the sub's
bid or promise was not reasonable and denied any recovery to
the contractor.
The ruling in this case suggests that subcontractors should
consider qualifying their bids and general contractors should
consider qualifying their solicitation for bids on a particular
contract form so that there is no occasion to disagree about
the contract terms after the price is relied upon in the general
contractor's bid. If this is not done, subcontractors may not
be held to their bids and may be able to extract concessions
or walk away from the job if the general contractor submits a
one-sided subcontract form.
Back to Top
Sub-Subcontractor's Claim Has Priority Over
State's Garnishment
Judge Crawford of the Franklin County Common Pleas Court has
ruled that a general contractor need not pay a subcontractor's
creditor, in this case the State of Ohio, pursuant to a garnishment
order, before paying an unpaid sub-subcontractor on an ODOT project.
The general contractor was holding money belonging to an insolvent
subcontractor when a garnishment order arrived seeking to have
these funds paid to the subcontractor's creditor —the State
of Ohio.
While the general contractor did not place the funds in a separate
account, it argued that it was holding them in trust and that
it could be forced to pay twice if the funds were seized in that
the sub-subcontractor was still owed money. The Court agreed
with the general contractor's argument that the money in effect
belonged to the sub-subcontractor rather than the insolvent subcontractor
and allowed the sub-subcontractor to be paid in full ahead of
the State of Ohio.
Back to Top
Suppliers of Subcontractors Have Bond
Rights
In a recent case of great interest to suppliers, subcontractors,
contractors and bonding companies, the Franklin County Court
of Appeals has ruled that suppliers of subcontractors have the
right to assert payment bond claims on public works projects
in Ohio.
Prior to the effective date of the new mechanic's lien and bond
law on January 1, 1992, Ohio law was that "subcontractors
of subcontractors" had lien rights but not bond rights and "suppliers
of suppliers" had bond rights but not lien rights, but at
least one bonding company argued that "suppliers of subcontractors" had
no right to make a payment bond claim. A trial court accepted
this interpretation but the Court of Appeals in the case of EFCO
v. Buckeye Union Insurance Company ruled in my client's
favor and reversed the decision of the trial court. The Court
of Appeals ruled that suppliers of subcontractors are not too
remote and can recover against public payment bonds.
This decision means that subcontractors and suppliers with pending "old
law" bond claims can recover, and is consistent with the
post January 1, 1992 "new law" which allows remote
tier subcontractors and suppliers to recover against the statutorily
required payment bond on public works.
As there is generally an indemnity agreement between the contractor
and his bonding company as to any losses under the bond, this
means that contractors who paid their subcontractors may have
to "pay twice" to any unpaid sub-subcontractors or
second-tier suppliers.
It is not enough for a general contractor to pay his bills and
trust that his subcontractors will do the same. Contractors who
do not want to "pay twice" for remote tier subcontractor
or supplier bond claims on public projects may want to consider
making lien waivers also serve as a bond waiver, inquiring as
to payment status of subs and suppliers, and issuing joint checks
to shaky subcontractors. Contractors should remember that the
Notice of Furnishing required of remote tier subcontractors and
suppliers to perfect mechanic's liens is not required to perfect
a bond claim.
Back to Top
Credits
Kegler, Brown, Hill & Ritter's Construction Law Newsletter is prepared by Donald W. Gregory for the Construction Law practice group.
To subscribe to any Kegler Brown publication, please use our Subscribe Form. To unsubscribe from any Kegler Brown publication, please use our Opt-Out Form. This publication, as well as an archive of previous publications, is also available from our Publications Archive.
The Construction Law Newsletter is designed to provide general information about the subjects discussed. It is not meant to be all-inclusive or comprehensive. Kegler Brown is not rendering any legal or professional advice by way of this publication.
© 1989-2008, Kegler, Brown, Hill & Ritter Co., L.P.A.
|