Fast-Track Interchange for Clermont County TID


Because of the fiscal impact of the recent recession, the Ohio Department of Transportation was forced to delay the vast majority of transportation construction projects in the state. Our client’s interchange was among those that were scheduled to be delayed for many years. Conferring with our client’s engineering and funding experts, we were able to devise a way to phase-in the job-creating project so that it would be less costly; other funding sources were also identified. We convinced the Ohio Department of Transportation to agree to these changes so that the interchange project was started earlier than originally scheduled – rather than being delayed.